Fire alarm monitoring and the duty to connect fire detection systems to the fire service

Who in Poland must connect a fire detection and alarm system to the Polish State Fire Service (PSP), where this obligation comes from, and what requirements the monitoring system operator meets. In the FireCom System, the operator is Orange Polska S.A.

What fire alarm monitoring is

A system for transmitting fire alarm and fault warning signals, commonly called fire alarm monitoring, automatically sends information about a fire from protected premises equipped with a fire detection and alarm system to the command post of the district or municipal headquarters of the State Fire Service. Transmission runs through the fire monitoring system operator, which supervises the operability of the system around the clock. In the FireCom System, the fire monitoring system operator is Orange Polska S.A., and the solution, the FireCom System, is supplied by F&K Consulting Engineers, partner of Orange Polska S.A.

Flow of a fire alarm from the protected premises to the State Fire Service The fire alarm control panel at the premises passes the alarm to the FireCom alarm transmission equipment. The equipment encrypts it with the per-premises encryption key and sends it simultaneously over two physically separate paths: a wired path in a dedicated VPN in an IP MPLS network with no connection to the Internet, and a GSM 4G LTE path in a dedicated APN, using an encrypted alarm transmission protocol with Contact ID event codes. Both paths lead to the retransmission station in the receiving centre of the operator, Orange Polska. Once the message has been permanently stored, the retransmission station sends an automatic technical acknowledgement (ACK) back to the transmitter, decrypts the alarm and retransmits it to the receiving station of the competent State Fire Service headquarters in parallel over two paths, wired and GSM. The receiving station receives the alarm and confirms receipt, and this receipt confirmation returns to the control panel at the premises on transmitter output PGM1. The receiving station automatically creates an incident entry in the headquarters' State Fire Service command support system SWD-ST (at headquarters integrated with SWD-ST); once the alarm is accepted, the entry is closed. Protected premises FACP fire alarm control panel FireCom EN 54-21 wired VPN in MPLS GSM 4G/LTE dedic. APN encrypted transmission premises key Operator's receiving centre Retransmission station message switching node decryption and retransmission to the receiving station of the relevant fire service HQ, in parallel: wired and GSM LAN GSM in parallel, TLS Fire Service HQ (local network) Receiving station receipt and confirmation, siren, lamps, display automatic incident entry SWD-ST alarm incident entry Duty officer accepts the alarm within time limit Receipt confirmation from the receiving station returns to the panel at the premises: transmitter output PGM1
The alarm travels over two physically separate paths simultaneously. The retransmission station in the operator's receiving centre (Orange Polska) automatically acknowledges receipt of the message to the transmitter (ACK) and retransmits the alarm to the receiving station of the competent State Fire Service headquarters in parallel over two paths, wired and GSM. It is the receiving station that receives the alarm and confirms receipt (output PGM1) and, at headquarters integrated with the State Fire Service command support system (SWD-ST), creates an incident entry in that system.

Legal basis of the obligation

In Poland, the obligation to connect a fire detection and alarm system to a State Fire Service unit stems from three legal acts.

Which premises must be connected

Under § 28 of the Regulation of 7 June 2010, the obligation to use a fire detection and alarm system and connect it to the State Fire Service headquarters applies, among others, to:

System participants and their roles

Owner or manager of the premises

Commissions the connection of the fire detection and alarm system to the monitoring system, signs a contract with the monitoring system operator (Orange Polska) and provides access to the premises for installation and maintenance of the alarm transmission equipment.

Monitoring system operator

In the FireCom System, this is Orange Polska S.A. It ensures transmission of alarms from protected premises to the State Fire Service, supervises system operability and maintains the receiving centre and the receiving stations. The FireCom System is supplied by F&K Consulting Engineers, partner of Orange Polska S.A.

District or municipal State Fire Service commander

Agrees the method of connection, provides a room for the receiving station and keeps a register of connected premises.

Obligations of the monitoring system operator

Requirements for the fire monitoring system operator (in the FireCom System: Orange Polska S.A.)
ObligationRequirement
Operation24/7 operation of the fault signal receiving station and the monitoring centre
Failure response timeCorrective action started no later than 2 hours after a failure is detected
Failure repair timeSystem operability restored no later than 24 hours
Training of State Fire Service staffFree training for command post staff in operating the receiving station, at least once a year
MaintenanceMaintenance of the receiving station at least once a year
ReportingAnnual statistical report on the number of alarms and fault warnings for the State Fire Service commander
Lists of premisesUp-to-date lists of monitored premises submitted to the State Fire Service commander by 1 January and 1 July each year

Why PSTN is no longer an option

Fire alarm transmission systems in Poland have so far relied on a VHF radio path and on the public switched telephone network (PSTN). The PSTN is being phased out across Europe, and a VHF system requires its own radio infrastructure.

The switch-off of the public switched telephone network and copper infrastructure is a Europe-wide process, driven by European Union regulatory policy and by operators' business decisions. For fire alarm transmission systems based on the PSTN, this means losing the transmission path with no way of replacing it with the same technology.

European Union regulatory framework

  • Directive (EU) 2018/1972: the European Electronic Communications Code (EECC), adopted on 11 December 2018. Article 81 governs migration from legacy infrastructure and the decommissioning of copper networks: operators with significant market power must notify the national regulator 2 to 3 years in advance before switching off elements of the copper network.
  • BEREC BoR (22) 109: the 2022 "Report on a consistent approach to migration and copper switch-off", based on data from 31 national regulatory authorities.
  • BEREC BoR (25) 66: the June 2025 "Progress Report on managing copper network switch-off". It confirms that in 17 of the 31 countries surveyed the operator with significant market power has announced a copper network switch-off schedule.
Status of PSTN switch-off in selected European countries
CountryOperatorStatusCompletion date
SpainTelefónicaCompleted27 May 2025 (8,532 copper exchanges closed)
EstoniaTeliaCompleted2017
NetherlandsKPNCompleted2019
SwitzerlandSwisscomCompleted2017
GermanyDeutsche TelekomCompletedAll-IP migration since 2014, most customers migrated by 2023
United KingdomBT/OpenreachIn progressNo new PSTN/ISDN services since September 2023; completion planned for January 2027
FranceOrange FranceIn progressNo new PSTN lines since November 2018; zone-by-zone switch-off until 2030
SwedenTeliaIn progressGradual switch-off of the copper network
PolandOrange PolskaPlannedCopper infrastructure switch-off has started; no official completion date

What an IP-based approach changes

Comparison of transmission technologies: VHF/PSTN and the FireCom System
FeatureVHF/PSTN technologiesFireCom System (IP)
Wired pathPSTN, analogue network, being phased outDedicated path in the separate Orange Polska IP MPLS network, with no connection to the Internet, secured at the interface with the premises; Type 1 link
Radio pathOwn VHF bandDedicated GSM 4G/LTE path set up in the operator's public network (dedicated APN and SIM cards); the radio licence for use of the path, granted on an exclusive basis, is held by the fire monitoring system operator, Orange Polska; Type 1 link
RedundancyRadio path and telephone pathTwo physically separate paths, with transmission initiated simultaneously and independently
InfrastructureOwn masts, transmitters, antennasTelecommunications operator's infrastructure
TransmissionVHF system radio protocols, telephone lineEncrypted alarm transmission protocol; Contact ID event codes
EncryptionDepends on the system manufacturerPer-premises encryption key on the premises-to-receiving-centre leg; TLS onwards to the station
IT integrationDepends on the system manufacturerOpen integration interfaces; the incident entry in SWD-ST is created by the headquarters' receiving station
CoverageVHF network coverageOperator's GSM network coverage and availability of a wired connection
Transmission mediumVHF radio band, PSTN telephone lineSeparate IP MPLS network and dedicated APN; neither path has Internet access

Two transmission paths in the FireCom System

FireCom sends every alarm simultaneously over two physically separate paths to the receiving centre of the fire monitoring system operator, Orange Polska, in line with the requirements of the Regulation of the Minister of the Interior and Administration for fire alarm transmission systems.

The FireCom System is a fire alarm transmission system based entirely on IP technology, with two dedicated, physically separate transmission paths: wired in a separate IP MPLS network and cellular GSM 4G/LTE in a dedicated APN, neither with access to the Internet. It does not depend on the PSTN infrastructure being phased out or on building its own VHF radio networks.