Who in Poland must connect a fire detection and alarm system to the Polish State Fire Service (PSP), where this obligation comes from, and what requirements the monitoring system operator meets. In the FireCom System, the operator is Orange Polska S.A.
A system for transmitting fire alarm and fault warning signals, commonly called fire alarm monitoring, automatically sends information about a fire from protected premises equipped with a fire detection and alarm system to the command post of the district or municipal headquarters of the State Fire Service. Transmission runs through the fire monitoring system operator, which supervises the operability of the system around the clock. In the FireCom System, the fire monitoring system operator is Orange Polska S.A., and the solution, the FireCom System, is supplied by F&K Consulting Engineers, partner of Orange Polska S.A.
The signal from the fire alarm control panel at the premises is transmitted to the alarm and fault receiving station installed at the command post of the State Fire Service headquarters. The station confirms correct receipt of the alarm, and the confirmation returns to the control panel at the premises on transmitter output PGM1.
Information about faults in the fire detection and alarm system, the transmission paths and the transmission equipment goes to the operator's fault receiving centre, not to the State Fire Service.
The operator's monitoring centre, Orange Polska, supervises the operability of all equipment and transmission paths, logs events and calculates system availability in line with EN 50136-1-1 (adopted in Poland as PN-EN 50136-1-1).
In Poland, the obligation to connect a fire detection and alarm system to a State Fire Service unit stems from three legal acts.
The Polish Act of 24 August 1991 on fire protection (consolidated text: Journal of Laws (Dz.U.) 2025 item 188, Article 5). It requires the owner, manager or user of a building, structure or site to equip it with fire signalling and alarm devices and to connect them to the nearest State Fire Service headquarters.
Regulation of the Polish Minister of the Interior and Administration (MSWiA) on the fire protection of buildings, other construction works and sites (Journal of Laws 2023 item 822, as amended, § 28, § 31). It defines the categories of premises required to install a fire detection and alarm system and the requirement to agree the method of connection with the territorially competent district or municipal State Fire Service commander.
Regulation of the Polish Minister of the Interior and Administration on the list of products used to ensure public safety or to protect health, life and property (Journal of Laws 2007 No. 143 item 1002, as amended). It sets out the technical requirements for systems transmitting fire alarm and fault warning signals, including requirements for transmission paths, equipment and system parameters.
Under § 28 of the Regulation of 7 June 2010, the obligation to use a fire detection and alarm system and connect it to the State Fire Service headquarters applies, among others, to:
With a fire zone area above the thresholds set out in the regulation
Theatres, cinemas, museums, entertainment halls
Hospitals, sanatoriums, hospices
And centres for people with disabilities
Metro stations, railway and bus stations, airports
Designated by the Director General of the State Archives
Commissions the connection of the fire detection and alarm system to the monitoring system, signs a contract with the monitoring system operator (Orange Polska) and provides access to the premises for installation and maintenance of the alarm transmission equipment.
In the FireCom System, this is Orange Polska S.A. It ensures transmission of alarms from protected premises to the State Fire Service, supervises system operability and maintains the receiving centre and the receiving stations. The FireCom System is supplied by F&K Consulting Engineers, partner of Orange Polska S.A.
Agrees the method of connection, provides a room for the receiving station and keeps a register of connected premises.
| Obligation | Requirement |
|---|---|
| Operation | 24/7 operation of the fault signal receiving station and the monitoring centre |
| Failure response time | Corrective action started no later than 2 hours after a failure is detected |
| Failure repair time | System operability restored no later than 24 hours |
| Training of State Fire Service staff | Free training for command post staff in operating the receiving station, at least once a year |
| Maintenance | Maintenance of the receiving station at least once a year |
| Reporting | Annual statistical report on the number of alarms and fault warnings for the State Fire Service commander |
| Lists of premises | Up-to-date lists of monitored premises submitted to the State Fire Service commander by 1 January and 1 July each year |
Fire alarm transmission systems in Poland have so far relied on a VHF radio path and on the public switched telephone network (PSTN). The PSTN is being phased out across Europe, and a VHF system requires its own radio infrastructure.
The switch-off of the public switched telephone network and copper infrastructure is a Europe-wide process, driven by European Union regulatory policy and by operators' business decisions. For fire alarm transmission systems based on the PSTN, this means losing the transmission path with no way of replacing it with the same technology.
| Country | Operator | Status | Completion date |
|---|---|---|---|
| Spain | Telefónica | Completed | 27 May 2025 (8,532 copper exchanges closed) |
| Estonia | Telia | Completed | 2017 |
| Netherlands | KPN | Completed | 2019 |
| Switzerland | Swisscom | Completed | 2017 |
| Germany | Deutsche Telekom | Completed | All-IP migration since 2014, most customers migrated by 2023 |
| United Kingdom | BT/Openreach | In progress | No new PSTN/ISDN services since September 2023; completion planned for January 2027 |
| France | Orange France | In progress | No new PSTN lines since November 2018; zone-by-zone switch-off until 2030 |
| Sweden | Telia | In progress | Gradual switch-off of the copper network |
| Poland | Orange Polska | Planned | Copper infrastructure switch-off has started; no official completion date |
| Feature | VHF/PSTN technologies | FireCom System (IP) |
|---|---|---|
| Wired path | PSTN, analogue network, being phased out | Dedicated path in the separate Orange Polska IP MPLS network, with no connection to the Internet, secured at the interface with the premises; Type 1 link |
| Radio path | Own VHF band | Dedicated GSM 4G/LTE path set up in the operator's public network (dedicated APN and SIM cards); the radio licence for use of the path, granted on an exclusive basis, is held by the fire monitoring system operator, Orange Polska; Type 1 link |
| Redundancy | Radio path and telephone path | Two physically separate paths, with transmission initiated simultaneously and independently |
| Infrastructure | Own masts, transmitters, antennas | Telecommunications operator's infrastructure |
| Transmission | VHF system radio protocols, telephone line | Encrypted alarm transmission protocol; Contact ID event codes |
| Encryption | Depends on the system manufacturer | Per-premises encryption key on the premises-to-receiving-centre leg; TLS onwards to the station |
| IT integration | Depends on the system manufacturer | Open integration interfaces; the incident entry in SWD-ST is created by the headquarters' receiving station |
| Coverage | VHF network coverage | Operator's GSM network coverage and availability of a wired connection |
| Transmission medium | VHF radio band, PSTN telephone line | Separate IP MPLS network and dedicated APN; neither path has Internet access |
FireCom sends every alarm simultaneously over two physically separate paths to the receiving centre of the fire monitoring system operator, Orange Polska, in line with the requirements of the Regulation of the Minister of the Interior and Administration for fire alarm transmission systems.
A dedicated path in the separate Orange Polska IP MPLS network, with no connection to the Internet, secured at the interface with the premises. Alarm traffic is fully isolated from public traffic. Every message is encrypted with the per-premises encryption key, and path continuity is continuously supervised: loss of the path is detected and reported as a fault. Type 1 link.
A dedicated transmission path set up in the public network of a telecommunications operator: a dedicated APN and dedicated SIM cards assigned to the devices, with no Internet access. The fire monitoring system operator, Orange Polska, holds a radio licence for use of the path, granted on an exclusive basis. The system does not use frequencies that do not require a radio licence. Type 1 link.
Two physically separate transmission paths, on which alarm transmission is initiated simultaneously and runs independently. Both qualify as Type 1 links, so either of them can act as the primary link. The links are bidirectional and allow receipt of every alarm message to be confirmed. The retransmission station acknowledges every message it has received and stored to the transmitter with an automatic technical acknowledgement (ACK); without it, the transmitter repeats the transmission. In addition, the receipt confirmation from the receiving station returns to the control panel at the premises on transmitter output PGM1, while a missing confirmation or loss of communication with the station is signalled on output PGM2 (a requirement of EN 54-21, adopted in Poland as PN-EN 54-21).
The FireCom System is a fire alarm transmission system based entirely on IP technology, with two dedicated, physically separate transmission paths: wired in a separate IP MPLS network and cellular GSM 4G/LTE in a dedicated APN, neither with access to the Internet. It does not depend on the PSTN infrastructure being phased out or on building its own VHF radio networks.